Ombersley Water Mains Replacement Works

Contact


For further information, please contact...

Rob Harris

Tel: 07805 301803


Balfour Beatty National Helpline (24 hours)

Tel: 0800 121 4444

 
Severn Trent Water

Category: Water Mains Replacement

Start Date: 22/06/2009

Anticipated Duration: 12 weeks

Work Status: Late

Reference: 1-0003

Roads Affected

Roundabout at the junction of Main Road and Droitwich Road, Ombersley;  Main Road;  Droitwich Road.

 

Description of Works

In order to carry out the remaining water mains replacement works in Ombersley, four way traffic lights will be in operation on the roundabout from 22nd June for approximately 4 weeks. Work will continue along the Droitwich Road to the junction of the A4133.

 

The next phase of works will commence from approximately the first week of July from the slip road on Main Road, continuing up to the roundabout and continuing from there up to the junction of Woodhall Lane.  Where necessary work will be carried out under two way traffic lights.

 

Further details can be found in the attached customer letter below.

Regular updates will also be posted on this site.

 


Work Updates

Subscribe to Live Updates     Live Updates Help


07 July 2009
Completion of Ombersley Roundabout Works

We are pleased to inform you the works on Ombersley roundabout will be completed on Wednesday 8th July, over a week ahead of schedule.  Work will now continue along the Droitwich Road to the junction of the A4133 and along Main Road to the junction of Woodhall Lane under two way traffic lights where necessary.

02 July 2009
Work Ahead of Schedule

We are pleased to announce that work on Ombersley roundabout is ahead of schedule.  Some reinstatement work will take place from Friday 3rd July and we will again be working over the weekend.

Further updates on our schedule will be posted early next week.

29 June 2009
Ombersley Roundabout

We are aware there are regular tailbacks as a result of the work on Ombersley roundabout. We would like to reassure you that we are looking at all possible options in order to minimise delays.  Work is also taking place at weekends in order to finish this section of work as quickly as possible.

In the meantime we would recommend using an alternative route, where possible, and would like to thank you for your patience and co-operation so far.