Category: Long Cycle Works

Start Date: 19/10/2009

Anticipated Duration: 48 weeks

Work Status: Current

Reference: 2-0014

Roads Affected

Crosby Ravensworth and Maulds Meaburn

 

Description of Works

We are currently carrying out the first phase of a £4.4 million mains sewerage project on behalf of United Utilities in both villages. This scheme will provide residents with the opportunity to connect into a new mains sewerage system which will help to reduce the instances of pollution to local rivers and watercourses.

 

The site operatives carrying out the main construction works on our behalf are employed by a local company with a wealth of experience in completing projects of this nature. They have recently successfully completed several similar schemes in North Cumbria. Many of their employees live in the local community and are very aware of the specific requirements of this type of rural location. They will be happy to help and advise on any day to day queries you may have during the works.

 

Due to the depth of the excavations required and the large plant and machinery used to lay the new pipes we will work in fenced- off areas approx.100 metres in length.

 

We will close these short sections of the road in both villages to all through traffic. We will reinstate and re-open individual sections of public highway before moving onto the next 100 metre length.

 

Local diversion routes will be sign-posted on surrounding roads leading to both villages. These signs which comply with Highway Authority requirements are in place to direct all types of vehicular traffic to the recommended alternative routes to enable them to safely avoid our construction areas.

 

Any other roads without diversion signage in place may not be suitable for all types of vehicles and are therefore not an approved alternative route around the works. We respectfully advise that you consider the suitability of any non sign-posted alternative route for your type of vehicle prior to its use.

 

We will do our best to minimise inconvenience to the local community and visitors to this idyllic part of Cumbria

 

We would like to take this opportunity to thank you for your patience and co-operation during this essential work to help  protect the local environment for future generations.

 

Additional Information relating to this project attached are:

 

·          preliminary schedule of the planned works in each village providing basic timescales for work affecting individual properties.

 

·          private pipe work connection process guidelines

 

 


Work Updates

Subscribe to Live Updates     Live Updates Help


16 November 2009
Latest Information

 Update 13th December 2009 Road Closures for Christmas Period

Back Lane Maulds Meaburn- road has been stoned up and compacted to allow residents access. Temporary road surface signage will be erected. We ask that residents and visitors please use due care and attention when accessing this area.

An official Highways Authority road closure is still in place to through traffic. Construction has been suspended untill 4th January 2010

Crosby Ravensworth- road re tarmaced up to current work areas. Full Vehicle access restored from Orton Scar.

Construction suspended until 4th January 2010

Refuse Collection Contractors have been notified.

Phase 1 - Crosby Ravensworth

Gang 1 - working o/s Butchers Arms P.H. towards property known as Lyvenet - anticipated duration 17 weeks

Current Access Restrictions

No vehicle access available past work areas into the centre of Crosby Ravensworth Village via Orton Scar Road

Residents access and parking facilities in direct work areas maintained as much as possible.

Pedestrian access maintained at all times

Local traffic diversion route signs in place on site - please follow diversion signs

 

Phase 1 - Maulds Meaburn

Gang 2 - Back Lane o/s Croft House working towards The Rowans - anticipated duration 12 weeks 

Start location revised due to archaeology constraints re: existing mill race - Ongoing consultations with English Heritage 

Current Access Restrictions

No vehicle access past direct work locations - work not directly affecting normal traffic flows through village

Pedestrian access maintained at all times

Normal vehicle access via Maulds Meaburn Village to Shap Road junction available

 

Related Documents
File Type Title & Description Link
[icon] - Microsoft Excel Crosby Ravensworth Schedule
Download 37 KB Download
[icon] - Microsoft Excel Maulds Meaburn Schedule
Download 37 KB Download
[icon] - Microsoft Word Private Connections Onsite Information
Download 35 KB Download
[icon] - Microsoft Word Public Meeting Letter
Download 34 KB Download
-
-