Category: Long Cycle Works
Start Date: 22/02/2010
Anticipated Duration: 22 Weeks
Work Status: Late
Reference: 2-0049
Roads Affected
Mersey Street
Green Lane
Wellbrow Drive
Description of Works
Work is being undertaken in Longridge to relieve properties of sewer flooding.
Work started on Mersey Street week commencing 22 February and this road will be closed for approximately 14 weeks. As the work moves on further updates will be posted.
There will be a compound on the grassed area on the corner of Green Lane and Wellbrow Drive, Longridge.
See attached letters