Manchester Ring Main Cleaning Project
Contact
For further information, please contact...
BBUS North West Customer Service Team
Tel: 0800 027 0310
Category: Large Diameter Trunk Mains Cleaning
Start Date: 01/04/2008
Anticipated Duration: 5 years
Work Status: Current
Reference: 2-0002
Roads Affected
Areas we will be working in are: Woodgate Hill to Heaton Park; Lostock to Speakmans Moor; Speakmans Moor to Heaton Park; Heaton Park to Denton;Denton to Speakmans Moor and the Godley area.
Description of Works
In April 2008 we started work on cleaning and repairing some of the main water pipes that supply customers in parts of Greater Manchester on behalf of United Utilities. We will be working on the Manchester ring main until March 2013. The main is a large water pipeline that circles the outskirts of the city and it supplies up to 560 million litres of water a day to over two million people in Manchester.
For more information please click on the brochure below.
The work will be carried out in 6 phases:
Phase 1 - April 2008 to June 2009 - Woodgate Hill to Heaton Park
Phase 2 - September 2008 to June 2009 - Lostock to Speakmans Moor
Phase 3 - July 2009 to March 2010 - Speakmans Moor to Heaton Park
Phase 4 - August 2010 to September 2011 - Heaton Park to Denton
Phase 5 - October 2011 to March 2013 - Denton to Speakmans Moor
Phase 6 - April 2010 to July 2010 - Godley area
You will receive advance warning of any works that may affect you in your area. Updates will also be posted on this website.